PTE / EPCC / 05
Solar Plant to Grid Connection
Grid connection for utility-scale and industrial solar generation projects, from the plant's collector system through step-up transformation to the utility connection point.
Defined project scope
One coordinated system, not disconnected packages
Power Tagun coordinates technical decisions, equipment interfaces, site delivery, testing, and handover around the approved system requirement.
Collector and evacuation system planning
Step-up transformer and switchgear selection
Protection, metering, and grid interface
Construction coordination and commissioning support
Typical equipment
Integrated around the single-line design
- 01Step-up transformers
- 02MV collector switchgear
- 03Protection and metering
- 04Grid interconnection equipment
Project outcomes
Coordinated grid interface
Traceable technical decisions
Commissioning-ready documentation
Delivery pathway
Controlled from engineering intent to energisation
- 01
Engineering
Define the system, studies, interfaces, and approved design basis.
- 02
Procurement
Match equipment, documentation, and delivery to the approved specification.
- 03
Installation
Coordinate site interfaces, installation quality, and construction readiness.
- 04
Testing
Verify protection, control, equipment, and system performance before energisation.
- 05
Commissioning
Control handover, energisation, and project records.